For people carrying out authorised routine sprinkler observations. Record the system and approved schedule and pin the valve set on a large site. Record the routine observations, with the clearance between stored goods and the sprinkler deflectors measured against the design minimum, and the gauge readings against the minimums in the approved schedule. Then record tests, any impairment and actions. Try the form below, see every question or open a completed example.
✎Every question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.
BAFSA describes routine checks and specialist maintenance for sprinkler-protected buildings. Use the system’s applicable standard, approved schedule and competent contractor advice; routine observations do not replace specialist servicing.
Pin the valve set on a large site, record the gauge readings against the minimums in your approved schedule, and measure the clearance between stored goods and the sprinkler deflectors. The form counts the observations needing action and flags anything below a minimum.
Pin the valve set
Mark current location at the valve room or pump house door, so a contractor or the fire service can find it on a large site. Mark current location works on web forms in any phone browser today, and the app version is on its way.
Enter the minimum clearance from the design or your contractor, then the smallest clearance seen, with a laser or from a photo with a 1.2 m pallet as the reference. Goods closer than the minimum show a note to lower them. It works on web forms in any phone browser today, and the app version is on its way.
Read the gauges as they stand and enter the minimum from the approved schedule or contractor. A reading below it shows a red note to treat it as a possible impairment and follow the site procedure. The form sets no figure of its own.
A fictional high-bay warehouse: both installations' gauges above the schedule minimum, the valve room pinned, a bent head guard above a dock door, and top-level pallets about 0.46 m below the deflectors against a 1.0 m design minimum, broken down the same day. Open it as a filled-in form, or switch to a blank copy and try it yourself.
This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.
Your team completes the sprinkler routine inspection on site in the SiteSurvey app on iPhone, iPad and Android phones and tablets. The project name and address fill in for them, it works without signal, and it syncs when the device is back online with photos kept against the question they answer.
Customers and subcontractors do not need the app: send them a link and they can fill it in from any browser.
Every question in the sprinkler routine inspection template
A sprinkler routine-check record with system identity, approved schedule, visual observations, authorised test references and impairment notifications. 6 sections and 59 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.
✎
Make it your own: every question is editable
This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.
Details you only enter once
Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.
Project: the project name
Site or premises address: the site address, from the space or the project
Client or organisation: the project's customer
1
Record details and scope
ProjectShort answer
Filled in from the project in SiteSurvey.
Fills in from the project name
Site or premises addressShort answer
Fills in from the site address, from the space or the project
Client or organisationShort answer
Fills in from the project's customer
Record date*Date
Person completing the record*Short answer
CheckFor trained persons working within an approved routine schedule. This is not system commissioning, hydraulic design verification or permission to operate valves or disable protection.
CheckCommercial sprinkler systems are inspected and maintained to BS EN 12845:2015+A1:2019, clause 20: the user carries out a weekly routine (gauges, water levels, main valve positions, water motor alarm test and automatic pump start test) and a competent contractor services the system quarterly, half-yearly and annually, with longer interval checks on top. Residential and domestic systems follow BS 9251:2021 instead. Article 17 of the Regulatory Reform (Fire Safety) Order 2005 requires fire safety equipment to be kept in efficient working order and good repair. BAFSA guidance supports both. Routine observations do not replace specialist servicing.
2
System and schedule
System, protected area and responsible person*Short answer
Control valve set locationShort answer
Optional. Mark current location at the valve room or pump house door, so a contractor or the fire service can find it on a large site.
Applicable standard and maintenance schedule*Short answer
Authorised procedure and checker training reference*Short answer
Last specialist service and open defectsShort answer
3
Routine observations
Visible heads and guards checked for damage or obstruction*Choose one
Acceptable
Action needed
Not checked
Not applicable
Action, limitation or reason not applicable*Notes
Conditional
Control valves observed in their documented normal state*Choose one
Acceptable
Action needed
Not checked
Not applicable
Action, limitation or reason not applicable*Notes
Conditional
Alarm panel and supply status observed*Choose one
Acceptable
Action needed
Not checked
Not applicable
Action, limitation or reason not applicable*Notes
Conditional
Protected areas checked for relevant storage or layout changes*Choose one
Acceptable
Action needed
Not checked
Not applicable
Action, limitation or reason not applicable*Notes
Conditional
Plant-room access and visible leaks checked*Choose one
Acceptable
Action needed
Not checked
Not applicable
Action, limitation or reason not applicable*Notes
Conditional
Minimum clearance below the sprinkler deflectors (m)Number
From the system design or the sprinkler contractor. The form does not set a figure.
Smallest clearance seen, top of the stored goods to the deflectors (m)Number
With a laser measure, or from a photo with a known object such as a 1.2 m pallet as the reference. A photo measure is rough: check close calls with a laser.
Clearance checkWorked out by the form
Conditional
CheckStored goods are closer to the sprinkler deflectors than the design minimum. Lower the stock and tell the responsible person and the sprinkler contractor.
Conditional
Observations needing actionWorked out by the form
Not checkedWorked out by the form
4
Gauges and weekly tests
Gauge readings
Repeat for each entry. Each one asks:
Installation or valve setShort answer
Pressure above the alarm valve (bar)Number
Pressure below the alarm valve (bar)Number
Minimum from the approved schedule or contractor (bar)Number
Readings against the minimumWorked out by the form
Conditional
Installations with a reading below the minimumWorked out by the form
WarningA gauge reading is below the minimum in the approved schedule. Treat it as a possible impairment: follow the site procedure, tell the responsible person and call the sprinkler contractor.
Conditional
CheckWeekly routine (BS EN 12845 clause 20). Record each test as it was done today.
Water motor alarm gong test (each alarm valve)Choose one
OK
Defect
Not tested
Automatic pump start testChoose one
OK
Defect
Not tested
No pumps
Main stop valves locked open in the correct positionChoose one
OK
Defect
Not tested
Water tank levels correctChoose one
OK
Defect
Not tested
No tanks
Pump start pressure (bar)Number
Conditional
Pump run time (minutes)Number
Conditional
Weekly tests with a defectWorked out by the form
WarningA weekly test failed. Treat it as a possible impairment: tell the responsible person and call the sprinkler contractor.
Conditional
Other authorised tests, results and report referencesNotes
5
Impairment and next checks
Impairment identified*Choose one
No impairment identified within scope
Impairment or uncertainty
Affected areas, responsible person notified and interim measures*Notes
Identify who was notified of an impairment, when and under which site procedure. Record restoration separately.
Shown when "Impairment identified" is "Impairment or uncertainty"
Specialist restoration and verification referenceShort answer
Observed condition evidencePhotos
Next weekly check dueDate
BS EN 12845 clause 20: every week.
Days to the next weekly checkWorked out by the form
Shown when "Record date" is answered and "Next weekly check due" is answered
CheckThe next due date is before the date of this visit. Check the date.
Conditional
Next contractor service dueDate
Set by the approved schedule: quarterly, half-yearly or annual service.
Days to the next serviceWorked out by the form
Shown when "Record date" is answered and "Next contractor service due" is answered
CheckThe next due date is before the date of this visit. Check the date.
Conditional
6
Actions and review
Are further actions required?*Choose one
Yes
No
Further action
Repeat for each further action. Each one asks:
Shown when "Are further actions required?" is "Yes"
Action and evidence reference*Notes
PriorityChoose one
Urgent
High
Medium
Low
Person responsible*Short answer
Target dateDate
Action status*Choose one
Open
In progress
Completed
Completion evidence*Notes
Shown when "Action status" is "Completed"
Outstanding limitations and information to pass onNotes
Record status*Choose one
Ready for review
Further work needed
Work or use stopped
Reviewed byShort answer
Review dateDate
Author signature*Signature
CheckSigning records the information entered. It does not itself certify legal compliance, remove a limitation or authorise unsafe work.
Scope and responsibility
For trained persons working within an approved routine schedule. This is not system commissioning, hydraulic design verification or permission to operate valves or disable protection.
What a useful entry looks like
Affected areas, responsible person notified and interim measures
Identify who was notified of an impairment, when and under which site procedure. Record restoration separately.
System impairment reported to the designated contact at the recorded time under procedure FS-11. Restoration evidence remains to be confirmed.
Fictional example of record wording. Use the actual evidence and approved arrangements for your job; this is not a completed report or an instruction to carry out the work.
See it filled in
A completed sprinkler routine inspection report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.
How should I record “Affected areas, responsible person notified and interim measures”?
Identify who was notified of an impairment, when and under which site procedure. Record restoration separately.
Does this prescribe weekly test steps?
No. Use the approved schedule for the particular system and record the work actually authorised.
Can a closed valve be opened without authorisation?
No. Follow the system procedure and escalation arrangements; the checklist does not grant operational authority.
What if a system is impaired?
Record affected areas, notification and interim measures, then link the restoration evidence.
What are the limits of this template?
For trained persons working within an approved routine schedule. This is not system commissioning, hydraulic design verification or permission to operate valves or disable protection.
Can I complete this form on site and share the record?
In the SiteSurvey app the form works offline, with photos and signatures recorded against the questions. Share the completed record as a PDF or a link. Dates and action owners are recorded fields; this form does not send reminders or update other systems.