The 25 hazards that come up most on construction, maintenance, installation, events and grounds work, with 135 control measures between them. Every control is placed in the hierarchy of controls, from removing the hazard to personal protective equipment as the last resort. The same library sits behind the tick list in our RAMS template and risk assessment template.

What is a control measure?

A control measure is anything you do to remove a hazard or reduce the risk from it: doing the job a different way, using a less harmful material, a guardrail or extraction, a permit, check or training, or protective equipment. The law expects you to remove risks where you can and to put collective measures before individual ones, so a good set of controls starts at the top of the hierarchy and uses PPE last.

Last updated . Facts checked by the SiteSurvey team on 24 October 2026 against HSE: Managing risks and risk assessment at work and Management of Health and Safety at Work Regulations 1999, Schedule 1.

Every hazard in the library

Hazards with a full page come first. Each shows how many controls it has, how they split across the hierarchy, and which of our completed example RAMS record it.

Asbestos

Asbestos survey or register checked for the area before work starts. Stop and get advice if unexpected materials are found. Licensed or trained work only on known materials.

5 controls across 2 levels · in 3 example RAMS

Hazards and control measures →

Biological hazards and sharps

Sharps not picked up by hand, litter picker and sharps box, gloves and covered skin, waste bagged and labelled, wash hands, needlestick first aid known.

5 controls across 3 levels · in 2 example RAMS

Hazards and control measures →

Chainsaws and cutting equipment

Users trained and certificated, chainsaw PPE worn, chain brake and guards checked, safe felling and cross-cutting methods, exclusion zone.

5 controls across 3 levels · in 1 example RAMS

Hazards and control measures →

Confined spaces

Avoid entry where the work can be done from outside. Where entry is needed: permit, gas testing, ventilation, rescue arrangements in place before entry, trained entrants and a top person.

6 controls across 4 levels · in 1 example RAMS

Hazards and control measures →

Crowds at build and breakdown

Build and breakdown done before doors open and after the venue is clear, site separated from the public, access controlled, vehicle movements marshalled.

5 controls across 3 levels · in 1 example RAMS

Hazards and control measures →

Electricity and live working

Isolate, lock off and prove dead before work. Live work only where it is unreasonable to work dead, with suitable precautions and competent people. 110 V or battery tools on site, RCD protection for 230 V.

6 controls across 5 levels · in 5 example RAMS

Hazards and control measures →

Excavation and underground services

Plans checked, CAT and Genny scan before and during digging, hand dig near services, sides supported or battered back, barriers and stop blocks, inspected at the start of each shift.

6 controls across 3 levels · in 1 example RAMS

Hazards and control measures →

Falling objects

Exclusion zone below the work, toeboards and brick guards, tools tethered, nothing stored at the edge, hard hats worn in the zone.

5 controls across 3 levels · in 5 example RAMS

Hazards and control measures →

Fire

Fire routes and exits kept clear, waste removed daily, flammables stored safely, extinguishers available, alarm and assembly point known to the crew.

5 controls across 3 levels · in 3 example RAMS

Hazards and control measures →

Fragile roofs and skylights

Fragile surfaces identified and signed, work from crawling boards or staging with guardrails, covers or guardrails on rooflights, nets or harness where needed.

5 controls across 4 levels · in 1 example RAMS

Hazards and control measures →

Hand-arm vibration

Low vibration tools, trigger times limited and shared, tools maintained and sharp, gloves and warm hands, symptoms reported.

5 controls across 3 levels · in 3 example RAMS

Hazards and control measures →

Hazardous substances and dust

COSHH assessment for each product, less harmful products where possible, dust suppressed at source with water or on-tool extraction, RPE where needed, skin protection, washing facilities.

6 controls across 4 levels · in 7 example RAMS

Hazards and control measures →

Hot works

Hot works permit, combustibles moved or covered, fire extinguisher at the work, fire watch during and after the work, gas bottles secured upright and checked.

7 controls across 4 levels · in 2 example RAMS

Hazards and control measures →

Lifting operations

Lift plan by an appointed person, equipment with a current thorough examination, loads slung by trained people, exclusion zone under the load, no lifting over people.

5 controls across 2 levels · in 5 example RAMS

Hazards and control measures →

Lone working

Lone working avoided for high risk tasks, check-in times agreed, phone or lone worker device carried, supervisor knows where the person is.

5 controls across 3 levels · in 2 example RAMS

Hazards and control measures →

Manual handling

Mechanical aids or two-person lifts for heavy or awkward loads, loads broken down, routes clear, people trained in lifting technique.

5 controls across 3 levels · in 8 example RAMS

Hazards and control measures →

Members of the public and building occupants

Work area fenced or barriered, signage, occupants told what is happening and when, routes kept open, noisy or dusty work timed to suit the building, no tools or materials left unattended.

6 controls across 3 levels · in 8 example RAMS

Hazards and control measures →

Noise

Quieter methods or equipment, noisy work scheduled away from others, hearing protection zones marked, hearing protection worn and in good condition.

4 controls across 4 levels · in 4 example RAMS

Hazards and control measures →

Overhead power lines

Lines identified before work, line owner consulted, barriers and goal posts where plant passes, no work beneath lines unless agreed safe, plant height restricted.

5 controls across 3 levels · in 1 example RAMS

Hazards and control measures →

Power tools and work equipment

Equipment checked before use, guards in place, faults reported and the equipment taken out of use, users trained, PAT or inspection records in date.

5 controls across 3 levels · in 1 example RAMS

Hazards and control measures →

Slips, trips and falls on the level

Routes kept clear, leads run at high level or covered, spills cleaned at once, good lighting, suitable footwear, waste cleared as the work goes.

6 controls across 4 levels · in 6 example RAMS

Hazards and control measures →

Temporary structures and rigging

Structures designed and built to the plan, competent riggers, loads within rating, checked and signed off before use, wind limits set and monitored.

5 controls across 2 levels · in 1 example RAMS

Hazards and control measures →

Vehicles and mobile plant

Pedestrians and vehicles separated, banksman for reversing, plant with working alarms and mirrors, hi-vis worn, drivers trained and authorised.

6 controls across 3 levels · in 6 example RAMS

Hazards and control measures →

Weather, heat and cold

Weather checked each day, work at height stopped in high wind, shade and water in heat, warm clothing and breaks in cold, lightning procedure.

5 controls across 1 levels · in 3 example RAMS

Hazards and control measures →

Work at height

Avoid working at height where the job can be done from the ground. Use a tower, MEWP or scaffold with guardrails before ladders. Check the equipment before use, keep the platform clear, and plan the rescue.

7 controls across 4 levels · in 7 example RAMS

Hazards and control measures →

Try it

Pick a hazard and choose its controls

Interactive

Try it: choose the controls for a hazard

Works the same way as the RAMS form. Nothing you tick is saved or sent anywhere.

2. Tick the controls in place or planned

Eliminate

Engineering control

Administrative control

Your controls, by level

  1. Eliminatenot ticked
  2. Substituteno control at this level for this hazard
  3. Engineeringnot ticked
  4. Adminnot ticked
  5. PPEno control at this level for this hazard

Nothing ticked yet.

3. Score the risk with these controls

Risk: choose likelihood and severity
Do this for real in the RAMS formSee the RAMS templateThe controls are a starting point from HSE guidance, not an assessment of your job.

How the controls split across the hierarchy

Across the whole library, most controls are physical safeguards or ways of working, a few remove or replace the hazard outright, and protective equipment is kept to the controls where nothing higher is possible.

  • Eliminate

    13

    controls

  • Substitute

    7

    controls

  • Engineering control

    30

    controls

  • Administrative control

    72

    controls

  • Personal protective equipment

    13

    controls

Common questions

Where do these controls come from?

Each control is written from HSE guidance for that hazard, and the library records the HSE page it follows. They are the controls an experienced supervisor would expect to see considered, in plain words. They are a starting point, not an assessment of a particular job: the right controls depend on the site, the work and the people.

Why are the controls grouped in levels?

Because controls are not equal. Removing the hazard protects everyone every time, a guardrail protects everyone without anyone having to do anything, and a harness only protects the person wearing it if they clip on. HSE's guidance and the general principles of prevention in the 1999 Regulations put collective measures before individual ones, and PPE last. The hierarchy of controls explained.

How is the library used in SiteSurvey?

In the RAMS and risk assessment forms, choosing a hazard brings up its controls as a tick list. You tick what applies and write how it works on your job. If only PPE is ticked the form warns you, and a hazard with no controls recorded counts as a point to resolve before the work starts. The form also suggests hazards that are likely from the type of work and the scope you wrote. How suggested controls work.

Is a hazard the same as a risk?

No. A hazard is anything that could cause harm: a fragile roof, a live cable, a trench. The risk is the chance that someone is harmed by it, and how badly. The RAMS form scores risk as likelihood times severity, each from 1 to 5, before and after any further action. What is a control measure?