Record an air balancing test terminal by terminal. Enter the acceptance band from the specification and each terminal's design and measured flow: the form works out the share of design, uses the retest where there is one, marks each terminal within, below or above the band, counts them and shows the lowest share (the index terminal). Try the form below, see every question or open a completed example.
✎Every question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.
Record the test terminal by terminal on a phone or tablet. Enter the acceptance band from the specification, the fan total and each terminal's design and measured flow: the form works out the share of design, uses the retest where there is one, marks every terminal within, below or above the band, counts them and shows the lowest share, the index terminal. The band comes from your specification; the form applies none of its own, and the recorded result stays the engineer's.
Each terminal against the band
Enter the design and measured flow for each terminal, and the retest after any adjustment. The form works out the final flow as a share of design and compares it with the band from the specification.
The form counts the terminals within, below and above the band and shows the lowest and highest share of design, so the index terminal for proportional balancing and anything still outstanding are clear.
A third floor fit-out at a fictional Newcastle office: eight supply terminals against a 90 to 110% band, S-3.03 trimmed from 114% to 104%, and S-3.05 still at 79% with the damper fully open, carried into the outstanding work with a kinked flexible duct to re-route. Open it as a filled-in form, or switch to a blank copy and try it yourself.
This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.
Every question in the air balancing report template
Record ventilation terminal design flows, measured readings, test conditions and outstanding work against project criteria. 4 sections and 53 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.
✎
Make it your own: every question is editable
This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.
Details you only enter once
Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.
Project or site: the project name
Client: the project's customer
Site address: the site address, from the space or the project
1
System and test references
Project or site*Short answer
Fills in from the project name
ClientShort answer
Fills in from the project's customer
Site addressShort answer
Fills in from the site address, from the space or the project
Record reference*Short answer
Record date*Date
Prepared by*Short answer
System or AHU reference*Short answer
Design drawing and revision*Short answer
Test procedure reference*Short answer
Instrument model and serial*Short answer
Calibration record and due date*Short answer
2
Test conditions
Operating mode, fan setting and conditions*Notes
Access limitations or none*Notes
Airflow unit for this record*Choose one
L/s
m³/h
CFM
CheckAir balancing is normally carried out to BSRIA BG 49/2015 (Commissioning air systems) and CIBSE Commissioning Code A (Air distribution systems), or to the project specification where it sets something different. The acceptance band and test method come from the specification or the procedure named on page 1, not from this form.
GuidanceAcceptance band Enter the band from the specification or the commissioning procedure the project uses, as a percentage of design (for example 90 to 110). The form compares every terminal with it; it sets no band of its own.
Lowest acceptable flow (% of design)Number
Highest acceptable flow (% of design)Number
Design total airflow at the fanNumber
In the airflow unit above. Leave blank if the fan total is not part of this test.
Measured total airflow at the fanNumber
From a duct traverse or the unit's flow measuring station.
Fan total as a share of design (%)Worked out by the form
Conditional
Fan total against the bandWorked out by the form
Shown when "Fan total as a share of design (%)" is answered and "Lowest acceptable flow (% of design)" is answered and "Highest acceptable flow (% of design)" is answered
GuidanceUse the same airflow unit for every design and measured value in this record. Record the applicable project acceptance criteria; this form does not prescribe tolerances.
3
Terminal readings
Terminal readings
Repeat for each terminal. Each one asks:
Terminal ID*Short answer
Room or location*Short answer
Air path*Choose one
Supply
Extract
Return
Design airflow*Number
Measured airflow*Number
Measured as a share of design (%)Worked out by the form
Conditional
Criterion, if different from the bandShort answer
Recorded result*Choose one
Meets stated criterion
Does not meet stated criterion
Not assessed
Adjustment or reason not assessed*Notes
Conditional
Retest airflowNumber
Final flow as a share of design (%)Worked out by the form
The retest if there is one, otherwise the first reading.
Conditional
Final flow against the bandWorked out by the form
Shown when "Final flow as a share of design (%)" is answered and "Lowest acceptable flow (% of design)" is answered and "Highest acceptable flow (% of design)" is answered
Retest record referenceShort answer
Terminals recordedWorked out by the form
Within the bandWorked out by the form
Below the bandWorked out by the form
Above the bandWorked out by the form
Lowest final share of design (%)Worked out by the form
The index terminal in proportional balancing: the one the others are set against.
Highest final share of design (%)Worked out by the form
CheckSome terminals are outside the band after any retest. Carry them into the outstanding work below with the next action and who owns it.
Conditional
Terminal identification or instrument photosPhotos
4
Review and outstanding work
Overall recorded status*Choose one
Complete against stated criteria
Outstanding work
Not assessed
Outstanding work or assessment limitations*Notes
Conditional
Defects and actions
Repeat for each action. Each one asks:
Action needed*Notes
PriorityChoose one
Urgent
High
Medium
Low
OwnerShort answer
Due dateDate
StatusChoose one
Open
In progress
Completed
PhotosPhotos
GuidanceThis is a readings record. It does not calculate airflow, certify system performance or replace the competent person’s commissioning assessment.
Tester signatureSignature
Reviewed byShort answer
Reviewer acknowledgementSignature
Client witness nameShort answer
Client witness signatureSignature
See it filled in
A completed air balancing report report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.
Record system and drawing references, test conditions, instruments, airflow units, terminal IDs, design and measured flows, project criteria and outstanding work.
Does the form calculate airflow or pass and fail results?
It works out each terminal's flow as a share of design and compares it with the band you enter from the specification. It does not derive airflow from velocity or apply a tolerance of its own, and the recorded result stays the engineer's.
How should retests be recorded?
Keep the original measured flow, describe the adjustment, record the retest flow and reference the retest record. Retain unresolved results in the summary.
Is this an HVAC maintenance checklist?