Bathroom remodel checklist
A bathroom remodel (renovation or refit) checklist for the contractor doing the job, filled in on a phone from the first walk-round to the handover. It records the scope and every selection agreed with the client, the room before work starts, anything found at strip-out and the variation agreed for it, then checks at rough-in, waterproofing before tiling, tiling and fixtures, and the final test of every outlet and the fan. If you are a homeowner, it shows what a good contractor checks at each stage; it is not a budget or shopping list. To measure up before quoting, use the bathroom survey.
For bathroom fitters, remodelers, builders and project managers who want a dated record, with photos, of what was agreed, found, checked and handed over.
One form for the US and the UK, with both terms where they differ (remodel or renovation, drywall or plasterboard, GFCI or RCD). Pick the country on page 1 to see the US code or England building regulations notes.
- Scope and selections room by room, with who supplies each item and the client's signature
- Strip-out findings such as rot or leaks, each with photos and a variation the client agrees in writing
- Stage checks for rough-in, waterproofing (tanking) before tiling, tiling and fixtures, and final tests
- Handover: what the client was shown, documents handed over, snags, actions and two signatures
Ready to use from the form library, and every question is yours to edit. Try it for a small trial fee, cancel any time.
Try it on your phone
Try it on this phone
Fill in the bathroom remodel on your phone now
See how the bathroom remodel looks on your phone
Scan the code with your phone camera. It opens the real form, no sign-up needed.
Open the live example and fill it in, just as your team would on site. No sign-up needed.
See it on this phoneEvery question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.
What should a bathroom remodel checklist include?
A bathroom remodel record is useful when it ties the job to what the client agreed and to photos of everything that gets covered up. The selections list with who supplies each item, the strip-out findings with a signed variation, and photos of the pipework and waterproofing before tiling are what settle questions later, when a tile cracks or a ceiling below gets a stain.
Last updated . Facts checked by the SiteSurvey team on 27 October 2026 against International Residential Code section M1505.2, recirculation of air (quoted by Knox County Code Administration and Inspection, Tennessee), Approved Document F: ventilation, volume 1 dwellings (GOV.UK), Building Regulations 2010, regulation 12, giving notice of building work, GOV.UK, building regulations approval, HSE, asbestos frequently asked questions, Control of Asbestos Regulations 2012, regulation 5, identification of the presence of asbestos and US EPA, lead Renovation, Repair and Painting Program.
How to use the bathroom remodel checklist
Start it at the walk-round with the client and fill in each page as the job reaches that stage.
Agree the scope
Walk the room with the client. Tick the work agreed, list every fixture and finish with who supplies it, note anything still to choose, record the permit or notification route, and get the client's signature.
Record the room before work
Photograph the room and the route through the home, agree existing damage, protect floors, isolate water and circuits, and check for asbestos or lead paint where the age of the home calls for it.
Log what strip-out finds
Add a finding for rot, leaks, mould or hidden services, with photos. If it is extra work, give it a variation reference, price and time, and record the client's decision before you do it.
Check each stage before it is covered
At rough-in check falls, supplies, the pressure test, the fan duct and backing. Check the waterproofing against the system maker's instructions and photograph it before tiling. Then check tiling and fixtures.
Test and hand over
Run every outlet, check the fan, sealant, grout and doors, scan the data labels and film the finished room. Show the client the valves and care rules, list snags, and sign together.
What makes a bathroom remodel record useful
Strip-out findings with the variation and the client's decision
Main bathroom, 1930s semi. Strip-out on 13 October: floorboards soft round the old WC, joist end wet and rotten for about 400 mm where it sits on the rear wall, from a long-term leak at the pan connector. Photographed, variation VO-01 for £480 and one extra day, agreed in writing the same day. New section bolted alongside and checked before the floor went back.
Fictional example. Record the actual evidence and approved arrangements for your job.
A common recording mistake
Fixing hidden rot or moving pipes without a written variation, then arguing about the extra at the end. The second is tiling a shower with no photo of the tanking at the corners and penetrations.
What happens next
Finish the snags, close the actions, and give the client the certificates, guarantees and the photos of the waterproofing and pipe runs.
Try the bathroom remodel form live
Answer a few questions and watch it adapt. Your answers are not saved, and any photos you add are deleted within the hour.
This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.
Want to see one filled in? See a completed bathroom remodel report (PDF), made by SiteSurvey from a fictional site visit.
Every question in the bathroom remodel template
A contractor's bathroom remodel (renovation) checklist: scope and selections agreed with the client room by room, existing condition and protection, strip-out findings handled as variations, rough-in, waterproofing before tiling, tiling and fixtures, final checks and a handover with care instructions, snags, actions and signatures, with US and England notes. 10 sections and 210 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.
Make it your own: every question is editable
This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.
Details you only enter once
Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.
- Project: the project name
- Site address: the site address, from the space or the project
- Client or owner: the project's customer
Job details
- ProjectShort answer
Filled in from the project in SiteSurvey.
Fills in from the project name - Site addressShort answerFills in from the site address, from the space or the project
- Client or ownerShort answerFills in from the project's customer
- Location (GPS)Short answer
- Walk-round date*Date
- Contractor representative*Short answer
- ContractorShort answer
- Quote, contract or job referenceShort answer
- Where is the job?*Choose one
Sets which notes you see. Local codes, amendments and the building control body decide what applies.
- US
- England
- Wales
- Scotland
- Northern Ireland
- Other country
- When was the home built?Choose one
- Before 1978
- 1978 to 1999
- 2000 or later
- Not known
- Planned startDate
- Planned finishDate
- Client contact on site (name and phone)Short answer
- CheckThis is the contractor's job record for a bathroom remodel (renovation or refit): the scope agreed with the client, checks at each stage and the handover. It is not building control or code approval, an electrical or gas certificate, or a guarantee. Falls, fixings, cure times and test values come from the fixture and system makers' instructions, the design and the local code.
- GuidanceUS, home built before 1978. EPA's Renovation, Repair and Painting (RRP) Rule requires anyone paid to do work that disturbs painted surfaces in homes built before 1978 to be certified, with workers trained in lead-safe work practices. Check what applies before strip-out.Shown only when the answers above make it relevant
- GuidanceGreat Britain, built before 2000. HSE says asbestos may be in any building built or refurbished before 2000, for example in pipe lagging, toilet cisterns and boards that look like plasterboard. An employer must not start work that could expose workers to asbestos until it has assessed whether asbestos is there, or assumes it is (Control of Asbestos Regulations 2012, regulation 5).Shown only when the answers above make it relevant
- Weather on siteAnswer
Scope and selections agreed with the client
- GuidanceWalk the room with the client. Agree what is being done, every fixture and finish, who supplies it, and anything still to choose. Anything that changes later goes on the variations list on page 4.
- Rooms in this jobRepeat for each room. Each one asks:
- Room*Short answer
For example main bathroom, en-suite, cloakroom WC.
- Work agreed in this roomTick all that apply
- Strip out the existing suite
- New bath
- New shower or walk-in shower
- Wet room (level-access shower)
- Basin and vanity unit
- WC
- Wall tiling
- Floor tiling or other floor finish
- Waterproofing (tanking)
- Underfloor heating
- Move waste or supply positions
- New or replacement extractor fan
- Lighting, shaver socket or heated towel rail
- Window or door change
- Ceiling, drywall (plasterboard) or plaster repairs
- Decoration
- Layout changing (fixtures moving position)?Yes or No
- What moves, and where toNotesShown when “Layout changing (fixtures moving position)?” is Yes
- Room length (mm or in)Number
Optional. Full dimensions belong on the bathroom survey.
- Room width (mm or in)Number
- Fixtures and finishes (selections)Repeat for each selection. Each one asks:
- Item*Short answer
For example bath, shower tray, basin and vanity, WC, tiles, taps, extractor fan.
- QuantityNumber
- Make, model or rangeShort answer
- Finish, colour or sizeShort answer
- Supplied byChoose one
- Contractor
- Client
- Not decided
- Client has confirmed this choice?Yes or No
- Needed on site byDateShown when “Client has confirmed this choice?” is No
- r_openWorked out by the form
- Photos of the room as it is nowPhotos
- Selections not yet confirmedWorked out by the form
- Permit or building control*Choose one
- Permit or building control application made
- Notified through a registered installer or competent person scheme
- Checked: not needed for this work
- Not yet checked
- Permit or application referenceShort answerShown when “Permit or building control” is “Permit or building control application made”
- GuidanceUS. The local building department decides which bathroom work needs a permit and which inspections it makes. Record the permit number here and each inspection result on the stage pages.Shown when “Where is the job?” is “US”
- GuidanceEngland. GOV.UK lists installing a bathroom that involves plumbing, and changing electrics near a bath or shower, among work that may need building regulations approval; you do not need to get approval yourself if the work is done by someone registered with a competent person scheme. Electrical work must be notified if it is a new circuit, a new consumer unit, or an addition or alteration to circuits in a special location, which includes the space around a bath or shower (Building Regulations 2010, regulation 12).Shown when “Where is the job?” is “England”
- CheckFind out before work starts. Starting without a needed permit or notice can mean opening up finished work later.Shown when “Permit or building control” is “Not yet checked”
- Access, working hours, parking, water and toilet arrangements while the room is out of useNotes
- Not included in this jobNotes
- Client signature: scope and selections agreedSignature
- Date agreedDate
Existing condition and protection
- Date checkedDate
- Checked byShort answer
- Photos taken of the room, and the route through the home, before work startsChoose one
Shows existing damage so it is not blamed on the job.
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Existing damage agreed with the client (walls, ceilings below, floors, doors)Choose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Floors, stairs and route protected; dust sheets or a dust screen at the doorChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Water isolated and the supplies capped or valved off; no leak after isolationChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Circuits for the room isolated and locked off by the electrician before strip-outChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Materials that may contain asbestos or lead paint identified before anything is disturbedChoose one
See the note on page 1 for the age of the home.
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Somewhere for waste agreed (skip or dumpster, permit if on the street)Choose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- A working toilet and wash facility available to the household during the jobChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Items needing actionWorked out by the form
- Not checkedWorked out by the form
- Existing damage noted with the clientNotes
- Photos before work startsPhotos
Strip-out findings and variations
- Date checkedDate
- Checked byShort answer
- Anything found during strip-out?*Yes or No
- Strip-out findingsRepeat for each finding. Each one asks:Shown when “Anything found during strip-out?” is Yes
- What was found*Choose one
- Rot or decay in the floor, joists or framing
- Leak or water damage
- Mould
- Pipes or cables not where expected
- Waste or drain problem
- Joists or studs cut or notched
- Possible asbestos
- Wall or ceiling not sound
- Other
- Where*Short answer
- What was found and what it needsNotes
- Photos of the findingPhotos
- Is this extra work (a variation or change order)?Yes or No
- Variation or change order referenceShort answerShown when “Is this extra work (a variation or change order)?” is Yes
- Price and time effectShort answerShown when “Is this extra work (a variation or change order)?” is Yes
- Client decisionChoose one
- Agreed in writing
- Waiting for the client
- Declined: recorded
Shown when “Is this extra work (a variation or change order)?” is Yes - Date of decisionDateShown only when the answers above make it relevant
- Needs a specialist (engineer, asbestos surveyor, electrician) before work continues?Yes or No
- sf_waitingWorked out by the form
- sf_holdWorked out by the form
- FindingsWorked out by the formShown when “Anything found during strip-out?” is Yes
- Variations waiting for the clientWorked out by the formShown when “Anything found during strip-out?” is Yes
- Waiting for a specialistWorked out by the formShown when “Anything found during strip-out?” is Yes
- WarningDo not carry out extra work until the client has agreed the variation in writing.Shown only when the answers above make it relevant
- WarningStop work on the affected area until the specialist has said what to do.Shown only when the answers above make it relevant
- Photos of the stripped room, every wall and the floorPhotos
Rough-in (first fix)
- Date checkedDate
- Checked byShort answer
- GuidanceUS. The International Residential Code (section M1505.2, as adopted locally) says bathroom exhaust air is not recirculated within the home and is exhausted directly to the outdoors, and that it must not discharge into an attic, crawl space or other area inside the building. Check the code and any local rules on where the vent may end.Shown when “Where is the job?” is “US”
- GuidanceEngland. Approved Document F says that when building work is done in a bathroom, existing extract fans should be kept or replaced, and any kept should be checked to see they work (paragraph 3.30). Table 1.1 gives 15 litres per second as the minimum rate for an intermittent bathroom extract fan.Shown when “Where is the job?” is “England”
- Waste positions and falls to the drawing and the fixture makers' instructionsChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Traps reachable for cleaning, access panels planned for anything boxed inChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Hot and cold supplies in the right positions, with isolation valves where specifiedChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Supply pipework pressure tested before it is coveredChoose one
Record the test and reading below.
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Shower valve set to the depth the maker gives for the finished wallChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Extractor fan ducted to a vent cap outside, not left discharging into a loft (attic), crawl space or other space inside the buildingChoose one
See the note below.
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Electrical work in the bath and shower area done and tested by a qualified electrician; GFCI or RCD protection as local code requiresChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Floor structure sound and repaired; joists not over-notched for new pipesChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Backing (noggins or blocking) in place for the basin, WC frame, grab rails, screens and towel railChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Items needing actionWorked out by the form
- Not checkedWorked out by the form
- Pressure test: required test and readingShort answer
For example the pressure and time from the specification or plumbing code, and what the gauge showed.
- Pressure test resultChoose one
- Pass
- Fail
- Not checked
- Not applicable
- rf_test_failWorked out by the form
- WarningThe pressure test failed. Fix the leak and test again before anything is covered.Shown when “Pressure test result” is “Fail”
- Rough-in (first fix) inspection by the building department or building controlChoose one
- Passed
- Failed: re-inspection needed
- Booked
- Not required
- Inspector and result referenceShort answerShown only when the answers above make it relevant
- Photos of every wall and the floor before cover-upPhotos
So pipes and cables can be found later without opening the wrong wall.
Waterproofing (tanking) before tiling
- Date checkedDate
- Checked byShort answer
- Is waterproofing (tanking) part of this job?*Yes or No
- Waterproofing system (maker and product)Short answerShown when “Is waterproofing (tanking) part of this job?” is Yes
- Areas waterproofedTick all that apply
- Shower walls
- Shower floor or tray area
- Whole floor
- Walls around the bath
- Behind the basin
- Other
Shown when “Is waterproofing (tanking) part of this job?” is Yes - GuidanceFollow the waterproofing system maker's instructions and the specification. This page records that they were followed; it does not set the method.Shown when “Is waterproofing (tanking) part of this job?” is Yes
- Backer board or substrate is the type the waterproofing maker allows, fixed and soundChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Primer applied where the system needs itChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Corners, board joints and wall to floor junctions reinforced with the system tapeChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Pipe and valve penetrations sealed with the system collars or sealantChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Number of coats and coverage as the maker says; no pinholes or thin spotsChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Waterproofing runs onto the shower tray or bath upstand, or to the drain, as the maker detailsChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Wet room floor falls to the drain with no pondingChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Left to cure for the time the maker gives before tilingChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
Shown when “Is waterproofing (tanking) part of this job?” is Yes - What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Items needing actionWorked out by the formShown when “Is waterproofing (tanking) part of this job?” is Yes
- Not checkedWorked out by the formShown when “Is waterproofing (tanking) part of this job?” is Yes
- Water test before tilingChoose one
A flood or spray test where the system maker or the specification calls for one.
- Passed
- Failed
- Not done
- Not required by the system or specification
Shown when “Is waterproofing (tanking) part of this job?” is Yes - How it was tested and for how longShort answerShown only when the answers above make it relevant
- wp_test_failWorked out by the form
- WarningThe water test failed. Repair and test again before any tiles go on.Shown when “Water test before tiling” is “Failed”
- Photos of the waterproofing before tilingPhotos
Corners, penetrations and the junction with the tray or bath. This is the only record once it is tiled.
Shown when “Is waterproofing (tanking) part of this job?” is Yes
Tiling and fixtures
- Date checkedDate
- Checked byShort answer
- Tile layout agreed with the client (start line, cuts, feature tiles) before fixingChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Tiles level and plumb, lines and joints even, cuts neatChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Grout complete and consistent, no gaps or pinholesChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Movement joints and junctions (bath, tray, worktop, corners) sealed as the tile and adhesive makers specifyChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Bath or tray bedded, level and supported as the maker saysChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- WC, basin and vanity fixed level and secure into backingChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Shower screen or enclosure fixed and sealed as the maker saysChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Access panels fitted for traps, valves or pumps that are boxed inChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Brassware fitted the right way round and tight; no damage to finishesChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Items needing actionWorked out by the form
- Not checkedWorked out by the form
- Photos of the tiling and fixturesPhotos
Final checks
- Date checkedDate
- Checked byShort answer
- Every tap, shower and outlet run; no leaks at any joint, trap or valveChoose one
Look under the bath and basin, and at the ceiling below.
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- WC flushes, refills and stops filling; no leak at the pan connectorChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Bath, basin and shower drain freelyChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Shower temperature and flow as expected; thermostatic valve workingChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Extractor fan runs, air comes out at the outside vent, any overrun or humidity control worksChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Sealant continuous and neat at the bath, tray, basin and worktopChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Grout complete, tiles clean, no cracked or chipped tilesChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Door and window open, close and latch; door undercut kept if specifiedChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Lights, shaver socket, heated towel rail and underfloor heating workChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Room clean, protection removed, waste taken awayChoose one
- Acceptable
- Action needed
- Not checked
- Not applicable
- What needs doing, or why not checkedNotesShown only when the answers above make it relevant
- Items needing actionWorked out by the form
- Not checkedWorked out by the form
- Final inspection by the building department or building controlChoose one
- Passed
- Failed: re-inspection needed
- Booked
- Not required
- Reference or certificate numberShort answerShown when “Final inspection by the building department or building control” is “Passed”
- Data labels (extractor fan, shower, towel rail)Scan a label: make, model, serial number
Optional. Scan the data plate or label to capture the numbers.
- Photos of the finished roomPhotos
- Filmed walk-round of the finished bathroomWalk Cam video with voice-to-text
Optional. Film a guided walk-round on the SiteSurvey app.
Handover and care instructions
- Handover dateDate
- Shown to the clientTick all that apply
- Where the water isolation valves and stop valve (stopcock) are
- How to clean the access panels and traps
- How the shower, fan and heating controls work
- Not to use the shower or bath until the sealant has cured for the time the maker gives
- How to clean the tiles, grout and fittings without damaging them
- Keep the fan running during and after a bath or shower
- Documents handed overTick all that apply
- Electrical certificate
- Building control completion certificate or final inspection record
- Product guarantees and instructions
- Waterproofing system record and photos
- Care and cleaning instructions
- Contractor workmanship guarantee
- Snags agreed at handover (punch list)Repeat for each snag. Each one asks:
- Snag (punch list item)*Short answer
- WhereShort answer
- PhotoPhotos
- Status*Choose one
- Open
- Fixed, checked
- sn_openWorked out by the form
- Snags still openWorked out by the form
- Client commentsNotes
Result, actions and sign-off
- Items needing actionWorked out by the form
- ResultWorked out by the form
- ActionsRepeat for each action. Each one asks:
- Action*Notes
- PriorityChoose one
- Urgent: stop work
- Before cover-up or tiling
- Before handover
- Agreed snag after handover
- Who will do it*Short answer
- Due byDate
- Status*Choose one
- Open
- In progress
- Done, checked
- Photo when donePhotosShown when “Status” is “Done, checked”
- Actions still openWorked out by the form
- Decision*Choose one
- Handed over
- Handed over with agreed snags to finish
- Not ready for handover
- Next check or re-inspection dateDate
- Summary for the clientNotes
- Contractor nameShort answer
- Contractor signature*Signature
- Client nameShort answer
- Client signatureSignature
See it filled in
A completed bathroom remodel report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.
Bathroom remodel FAQs
Is this checklist for homeowners or contractors?
It is the contractor's job record: what was agreed with the client, what was found and checked at each stage, and what was handed over. Most people searching for a bathroom renovation checklist are homeowners, and it is useful to them too, because it shows what a good contractor checks and photographs before each stage is covered up. It is not a budget, a design guide or a shopping list.
Does a bathroom renovation need building regulations approval in England?
It can. GOV.UK lists installing a bathroom that involves plumbing, and changing electrics near a bath or shower, among work that may need approval, and says you do not need to get approval yourself if you use someone registered with a competent person scheme. Electrical work must be notified if it is a new circuit, a new consumer unit, or an addition or alteration to circuits in a special location, which includes the space around a bath or shower (Building Regulations 2010, regulation 12). In the US, the local building department decides which work needs a permit.
Sources: GOV.UK, building regulations approval and Building Regulations 2010, regulation 12, giving notice of building work.
Where must a bathroom extractor fan vent to?
Outside. Under the International Residential Code (section M1505.2, as adopted locally), bathroom exhaust air is not recirculated in the home and is exhausted directly to the outdoors, and it must not discharge into an attic, crawl space or other area inside the building. In England, Approved Document F says that when building work is done in a bathroom, existing extract fans should be kept or replaced and checked to work, and its Table 1.1 gives 15 litres per second as the minimum rate for an intermittent bathroom extract fan.
Sources: International Residential Code section M1505.2, recirculation of air (quoted by Knox County Code Administration and Inspection, Tennessee) and Approved Document F: ventilation, volume 1 dwellings (GOV.UK).
Do I need to check for asbestos or lead paint before stripping out an old bathroom?
Yes, where the age of the home calls for it. HSE says asbestos may be in any building built or refurbished before 2000, including in toilet cisterns, pipe lagging and boards that look like plasterboard, and an employer must assess whether it is present, or assume it is, before work that could disturb it (Control of Asbestos Regulations 2012, regulation 5). In the US, EPA's Renovation, Repair and Painting Rule requires anyone paid to disturb painted surfaces in homes built before 1978 to be certified and trained in lead-safe work practices.
Sources: HSE, asbestos frequently asked questions, Control of Asbestos Regulations 2012, regulation 5, identification of the presence of asbestos and US EPA, lead Renovation, Repair and Painting Program.
What should be checked before a shower is tiled?
The waterproofing (tanking). The form checks that the backer board suits the system, corners and joints are taped, pipe penetrations are sealed with the system's collars, the coats are complete, the membrane meets the tray or bath correctly and it has cured for the time the maker gives. It records any water test the maker or specification asks for, and photos of every corner and penetration, because once the tiles are on those photos are the only record.
What happens if rot or a leak is found during strip-out?
Record it as a finding with photos, say what it needs, and if it is outside the agreed price, give it a variation (change order) reference with the price and time it adds. The form counts variations still waiting for the client and shows a warning until the client agrees in writing, and holds work where a specialist such as an engineer or asbestos surveyor needs to see it first.
Related
Related templates
Templates that go with the bathroom remodel form
A bathroom measure survey: room size and height, every wall with its features, window and door, existing suite, water, waste, soil stack and electrics, extraction, floor, the new layout wanted and the customer's signature.
A waterproofing installation record covering system specification, substrate, joints, penetrations, concealment evidence, authorised tests and repairs.
Snag by snag record with room, element, photo and priority, checks with no snag, totals and re-inspection.
A customer handover pack record: completion and handover dates, certificates in the pack and to follow, manuals, warranties and keys, each system demonstrated, where the controls and shut-offs are, outstanding items, aftercare and the customer's signature.